π Lecture 39 β Supply Chain Management
π Overview: This lecture introduces the concept of supply chain management, its necessity, and benefits. It also delves into the logistics function as a critical element of the supply chain, covering evaluation of shipping alternatives, distribution requirements planning, and the role of electronic data interchange. This knowledge is fundamental for operations managers to ensure efficient flow of materials and information.
ποΈ Topics Covered
The lecture begins by defining a supply chain and outlining the need for and benefits of supply chain management. It then details the key elements of supply chain management with their typical issues. The core concepts of Logistics are explained, including its characteristics and a method for evaluating shipping alternatives (with a worked example). The lecture concludes with Distribution Requirements Planning (DRP) , Electronic Data Interchange (EDI) , and the Efficient Consumer Response (ECR) initiative, finally summarizing the key components of a successful supply chain.
π Lecture Summary
Supply Chain
The sequence of organizationβs facilities, functions, and activities that are involved in producing and delivering a product or service.
Need for Supply Chain Management
- Improve operations
- Increasing levels of outsourcing
- Increasing transportation costs
- Competitive pressures
- Increasing globalization
- Increasing importance of e-commerce
- Complexity of supply chains
- Manage inventories
Benefits of Supply Chain Management
- Lower inventories
- Higher productivity
- Greater agility
- Shorter lead times
- Higher profits
- Greater customer loyalty
Elements of Supply Chain Management
| Element | Typical Issues |
|---|---|
| Customers | Determining what customers want |
| Forecasting | Predicting quantity and timing of demand |
| Design | Incorporating customer wants, mfg., and time |
| Processing | Controlling quality, scheduling work |
| Inventory | Meeting demand while managing inventory costs |
| Purchasing | Evaluating suppliers and supporting operations |
| Suppliers | Monitoring supplier quality, delivery, and relations |
| Location | Determining location of facilities |
| Logistics | Deciding how to best move and store materials |
Logistics
The goal of logistic work is to manage the completion of project life cycles, supply chains and resultant efficiencies. Often Logistics is termed as the art and science of managing and controlling the flow of goods, energy, information and other resources like products, services, and people, from the source of production to the marketplace. It also refers to the movement of materials and information within a facility and to incoming and outgoing shipments of goods and materials in a supply chain.
Logistics is the time related positioning of resources and is commonly seen as a branch of engineering which creates "people systems" rather than "machine systems." It involves the integration of information, transportation, inventory, warehousing, material handling, and packaging.
Important Characteristics of Logistics
- Movement within the facility
- Bar coding
- Incoming and outgoing shipments
- EDI (Electronic Data Interchange)
- Distribution
- JIT Deliveries
Logistics: Evaluating Shipping Alternatives
A situation that arises frequently in some businesses in making a choice between quicker (expensive) shipping alternatives such as overnight or 2 day air and slower but cheaper alternatives. The decision in such cases often focuses on the cost savings of alternatives versus the increased holding cost that result from using slower alternative. Often the supplier gets paid on delivery of the product through EDI the very same time the order reaches its destination. The Incremental Holding cost incurred by using the slower alternative is computed as follows:
π Definition β Incremental Holding Cost: The additional cost of holding inventory for the extra time a slower shipping option takes. π Formula: Incremental Holding Cost = H ( d/365) Where:
- H = Annual Holding cost for the item.
- d = Time savings in days (the difference in transit time between the faster and slower option).
- d/365 = fraction of year saved.
Logistics Example
Determine the shipping alternative (within Pakistan) for a Karachi based Montessori toy manufacturer: 1 day or 5 days are best when the holding cost of the item is Rs. 100,000 per year. The 1 day shipping cost is Rs. 1500, the 3 day shipping cost is Rs. 600, and the 5 day shipping cost is Rs. 500.
Solution
- H = Rs. 100,000 per year
- Time savings for 1-day vs. 3-day = 3 days - 1 day = 2 days.
- Holding cost for additional 2 days = 100,000 X (2/365) = Rs. 547.95 β Rs. 548.
- Or, Holding cost per day = Rs. 274
Alternative A (Comparison: 1 day vs. 3 days)
- Cost savings by using 3-day option = Rs. (1500 - 600) = Rs. 900.
- Because the cost savings of Rs. 900 is more than the incremental holding cost of Rs. 548, use the 3 day option.
Alternative B (Comparison: 1 day vs. 5 days)
- Cost savings by using 5-day option = Rs. (1500 - 500) = Rs. 1000.
- Because the cost savings of Rs. 1000 is greater than the incremental holding cost of Rs. 548, use the 5 day option.
π‘ Why this matters: The decision rule is simple: if the cost savings from using a slower option are greater than the incremental holding cost incurred, the slower (cheaper) option is more cost-effective.
Distribution Requirements Planning
Distribution requirements planning (DRP) is a system for inventory management and distribution planning. It extends the concepts of MRPII.
Uses of DRP
Management uses DRP to plan and coordinate:
- Transportation
- Warehousing
- Workers
- Equipment
- Financial flows
Electronic Data Interchange
EDI is the direct transmission of inter-organizational transactions, computer-to-computer, including purchase orders, shipping notices, and debit or credit memos.
Electronic Data Interchange gives an organization the following benefits and advantages.
- Increased productivity
- Reduction of paperwork
- Lead time and inventory reduction
- Facilitation of just-in-time systems
- Electronic transfer of funds
- Improved control of operations
- Reduction in clerical labor
- Increased accuracy
Efficient Consumer Response
Efficient consumer response (ECR) is a supply chain management initiative specific to the food industry. ECR reflects companiesβ efforts to achieve quick response using EDI and bar codes.
E-Commerce: is the use of electronic technology to facilitate business transactions.
Successful Supply Chain
- Trust among trading partners
- Effective communications
- Supply chain visibility
- Event-management capability a. The ability to detect and respond to unplanned events
- Performance metrics
β Key Takeaways
Supply Chain Management is fundamentally about the flow of information that ensures the effective flow of materials from suppliers (upstream) to the organization and then to customers (downstream). A key operational decision involves evaluating shipping alternatives by comparing cost savings against incremental holding costs. Technologies like DRP and EDI are critical for planning, coordination, and efficient transactions. Ultimately, a successful supply chain is built on trust, effective communication, visibility, and the ability to respond to unplanned events, remembering that the chain is only as strong as its weakest link.
π§ Quick Revision Questions
- What is the formula for calculating the Incremental Holding Cost when evaluating shipping alternatives, and what does each variable represent?
- List four key elements of Supply Chain Management and one typical issue associated with each.
- What is Distribution Requirements Planning (DRP) , and what five areas does management use it to plan and coordinate?
- List five benefits of using Electronic Data Interchange (EDI) for an organization.
- According to the lecture, what are the key components of a Successful Supply Chain?
π Lecture 40 β Supply Chain Management (Contd.)
π Overview: This lecture continues the exploration of Supply Chain Management by examining key performance metrics and collaborative processes that enable effective supply chain design and analysis. It introduces the Supply Chain Operational Reference (SCOR) Metrics framework, the CPFR collaborative planning process, and critical concepts like Velocity and the Bullwhip Effect that challenge supply chain effectiveness.
ποΈ Topics Covered
This lecture covers the Supply Chain Operational Reference (SCOR) Metrics framework across four perspectives: Reliability, Flexibility, Expenses, and Assets/Utilization. It then discusses the Collaborative Planning, Forecasting and Replenishment (CPFR) process, followed by steps for creating an effective supply chain. The lecture examines supply chain performance drivers including Velocity (both inventory and information velocity), challenges to effective SCM, various trade-offs (including Bullwhip Effect, Cross-docking, Delayed Differentiation, and Disintermediation), supply chain issues at strategic, tactical, and operating levels, benefits and drawbacks of supply chain improvements, supplier partnerships, critical issues in technology management, and operations strategy.
π Lecture Summary
Supply Chain Operational Reference (SCOR) Metrics
The Supply Chain Operational Reference (SCOR) Metrics provide a standardized framework for evaluating supply chain performance across four key perspectives: Reliability, Flexibility, Expenses, and Assets/Utilization.
Under Reliability, metrics include on-time delivery, order fulfillment lead time, fill rate (fraction of demand met from stock), and perfect order fulfillment. Flexibility metrics cover supply chain response time, upside production flexibility, and agility to obtain competitiveness. Expenses are measured through supply chain management costs, warranty cost as a percent of revenue, and value added per employee. Assets/Utilization metrics include total inventory days of supply, cash-to-cash cycle time, and net asset turns.
π‘ Why this matters: Supply chain response time often makes or breaks a supply chain, making these metrics critical for operational success.
CPFR
CPFR stands for Collaborative Planning, Forecasting and Replenishment. It focuses on information sharing among trading partners. Forecasts can be frozen and then converted into a shipping plan. This process eliminates typical order processing.
The CPFR Process consists of the following steps:
- Step 1 β Front-end agreement
- Step 2 β Joint business plan
- Steps 3-5 β Sales forecast
- Steps 6-8 β Order forecast collaboration
- Step 9 β Order generation/delivery execution
Creating an Effective Supply Chain
To create an effective supply chain, organizations should:
- Develop strategic objectives and tactics.
- Integrate and coordinate activities in the internal supply chain.
- Coordinate activities with suppliers and with customers.
- Coordinate planning and execution across the supply chain.
- Form strategic partnerships.
Supply Chain Performance Drivers
The key performance drivers for a supply chain are:
- Quality
- Cost
- Flexibility
- Velocity
- Customer service
Velocity
Velocity in supply chains has two distinct meanings:
Inventory velocity: The rate at which inventory (material) goes through the supply chain. This measures how quickly physical goods move from suppliers to customers.
Information velocity: The rate at which information is communicated in a supply chain. This measures how quickly data and knowledge flow between trading partners.
Challenges to an Effective Supply Chain Management
Several challenges face effective SCM:
- Barriers to integration of organizations
- Getting top management on board
- Dealing with trade-offs
- Small businesses
- Variability and uncertainty
- Long lead times
Trade-offs
Supply chain management involves several critical trade-offs:
-
Cost-customer service
- Disintermediation: Reducing one or more steps in a supply chain by cutting out one or more intermediaries.
-
Lot-size-inventory
- Bullwhip Effect: Represents the real-life situation that inventories are progressively larger moving backward through the supply chain. This means small changes in customer demand create amplified fluctuations in orders placed upstream.
-
Inventory-transportation costs
- Cross-docking: The fact that goods arriving at a warehouse from a supplier are unloaded from the supplier's truck and loaded onto outbound trucks. This avoids warehouse storage.
-
Lead time-transportation costs
-
Product variety-inventory
- Delayed differentiation: The production of standard components and subassemblies, which are held until late in the process to add differentiating features.
Supply Chain Issues
Supply chain issues can be categorized into three levels:
Strategic Issues: Design of the supply chain, partnering.
Tactical Issues: Inventory policies, purchasing policies, production policies, transportation policies, quality policies.
Operating Issues: Quality control, production planning and control.
Supply Chain Benefits and Drawbacks
| Problem | Potential Improvement | Benefits | Possible Drawbacks |
|---|---|---|---|
| Large inventories | Smaller, more frequent deliveries | Reduced holding costs | Traffic congestion, increased costs |
| Long lead times | Delayed differentiation, Disintermediation | Quick response | May not be feasible, may need to absorb functions |
| Large number of parts | Modular | Fewer parts, simpler ordering | Less variety, cost, quality |
| Variability | Shorter lead times, better forecasts | Able to match supply and demand | Less variety |
Supplier Partnerships
Supplier partnerships can generate significant value through:
- Ideas from suppliers could lead to improved competitiveness
- Reduce cost of making the purchase
- Increase Revenues
- Enhance Performance
Critical Issues
Technology management in supply chains involves weighing:
- Benefits
- Risks
Strategic importance encompasses:
- Quality
- Cost
- Agility
- Customer service
- Competitive advantage
Operations Strategy
Key strategic insights for operations:
- SCM creates value through changes in time, location and quantity.
- SCM creates competitive advantage by integrating and streamlining the diverse range of activities that involve purchasing, internal inventory, transfers, and physical distribution.
β Key Takeaways
The SCOR metrics framework provides a comprehensive way to measure supply chain performance across reliability, flexibility, expenses, and asset utilization. The CPFR process enables collaborative planning through nine structured steps that move from front-end agreements through to order generation. The Bullwhip Effect represents a critical challenge where inventory levels increase progressively backward through the supply chain, and managers must understand trade-offs between cost-customer service, lot-size-inventory, and other competing priorities. Velocity in supply chains has two dimensionsβinventory velocity and information velocityβboth essential for performance. Effective SCM requires addressing barriers to integration, getting top management buy-in, and recognizing that implementation often fails due to lack of employee training and top management commitment.
π§ Quick Revision Questions
- What are the four perspectives of the SCOR Metrics framework, and name one metric for each perspective?
- What does CPFR stand for, and what are the three main focuses of this process?
- Explain the Bullwhip Effect and why it occurs in supply chains.
- What is the difference between inventory velocity and information velocity in a supply chain?
- List four trade-offs that supply chain managers must address and name the specific technique associated with each.
π Lecture 41 β SCHEDULING
π Overview: This lecture introduces the fundamental concepts of scheduling in production and operations management. It explains how scheduling impacts productivity in both manufacturing and service industries, covers scheduling approaches for high-volume, intermediate-volume, and low-volume (job shop) systems, and provides practical tools like Gantt Charts and the Assignment Method for optimal resource allocation.
ποΈ Topics Covered
The lecture begins with defining scheduling and its benefits, then distinguishes between high-volume flow systems and intermediate-volume systems with an economic run size formula. It covers low-volume job shop scheduling, including loading and sequencing, and explains Gantt Load Charts and Schedule Charts. The lecture details seven loading types and provides a comprehensive step-by-step walkthrough of the Hungarian Method for the Assignment Model, complete with a full numerical example.
π Lecture Summary
Scheduling
Scheduling is an important tool for manufacturing and service industries where it can have a major impact on the productivity of a process. In manufacturing, the purpose of scheduling is to minimize the production time and costs, by telling a production facility what to make, when, with which staff, and on which equipment. Similarly, scheduling in service industries, such as airlines and public transport, aims to maximize the efficiency of the operation and reduce costs.
Modern computerized scheduling tools greatly outperform older manual scheduling methods. This provides the production scheduler with powerful graphical interfaces which can be used to visually optimize real-time workloads in various stages of the production, and pattern recognition allows the software to automatically create scheduling opportunities which might not be apparent without this view into the data. For example, an airline might wish to minimize the number of airport gates required for its aircraft, in order to reduce costs, and scheduling software can allow the planners to see how this can be done, by analyzing time tables, aircraft usage, or the flow of passengers.
Companies use backward scheduling and forward scheduling to plan their human and material resources. Backward scheduling is planning the tasks from the due date to determine the start date and/or any changes in capacity required, whereas forward scheduling is planning the tasks from the start date to determine the shipping date or the due date.
π Definition β Scheduling: Establishing the timing of the use of equipment, facilities and human activities in an organization.
π‘ Why this matters: Effective scheduling is the backbone of operational efficiencyβgetting it right reduces costs and increases productivity across all types of organizations.
Benefits of Scheduling
Effective scheduling can yield cost savings and increases in productivity. The benefits of production scheduling include:
- Process change-over reduction
- Inventory reduction, leveling
- Reduced scheduling effort
- Increased production efficiency
- Labor load leveling
- Accurate delivery date quotes
- Real time information
High-Volume Systems
- Flow system: High-volume system with standardized equipment and activities
- Flow-shop scheduling: Scheduling for high-volume flow system
The flow system is illustrated as: Work Center #1 β Work Center #2 β Output
Scheduling Manufacturing Operations
Scheduling addresses four types of operations: β’ High-volume β’ Intermediate-volume β’ Low-volume β’ Service operations
High-Volume Success Factors
β’ Process and product design β’ Preventive maintenance β’ Rapid repair when breakdown occurs β’ Optimal product mixes β’ Minimization of quality problems β’ Reliability and timing of supplies
Intermediate-Volume Systems
Outputs are between standardized high-volume systems and made-to-order job shops. Key considerations include run size, timing, and sequence of jobs.
π Formula β Economic run size:
Qβ = β(2DS/H) Γ β(p/(p-u))
Where:
D = annual demand
S = setup cost
H = holding cost per unit per year
p = production rate
u = usage rate
β This formula determines the optimal batch size that minimizes total inventory and setup costs.
Scheduling Low-Volume Systems
β’ Loading - assignment of jobs to process centers β’ Sequencing - determining the order in which jobs will be processed β’ Job-shop scheduling - Scheduling for low-volume systems with many variations in requirements
Gantt Load Chart
A Gantt chart is used as a visual aid for loading and scheduling.
π Definition β Load chart: A type of Gantt Chart that shows the loading and idle times for a group of machines or list of departments.
The lecture provides a sample Load Chart showing Work Centers 1-4 with jobs scheduled across Monday through Friday. For example, Work Center 1 has Job 3 on Monday-Tuesday and Job 4 on Wednesday-Thursday.
π Definition β Schedule chart: A type of Gantt Chart that shows the orders or jobs in progress and whether they are on schedule or not.
π Definition β Input/Output Control Chart: A type of Control Chart that shows management of work flow and queues at the work centers.
Loading Types
The common types of loading include the following:
- Infinite loading β Jobs are assigned to work centers without regard to the capacity of the work center.
- Finite loading β Jobs are assigned to work centers with regard to the capacity of the work center and job processing times.
- Vertical loading β Loading jobs at a work center, job by job, usually according to some priority criterion, using infinite loading.
- Horizontal loading β Loading each job on all work centers it will require, then the next job on all work centers, according to some priority, using finite loading.
- Forward scheduling β Scheduling ahead, from some point in time.
- Backward scheduling β Scheduling by working backwards from the due date.
- Schedule chart β A Gantt chart that shows the orders or jobs in progress and whether they are on schedule or not.
Assignment Method of Linear Programming
The Assignment Model is a type of linear programming model for optimal assignment of tasks and resources. The Hungarian method is the method of assigning jobs by a one-for-one matching to identify the lowest cost solution.
The Hungarian Method proceeds through the following steps:
Step 1: Acquire the relevant cost information and arrange it in tabular form.
Step 2: Obtain the Row Reduction β subtract the smallest number in each row from every number in the row. Enter the results in a new table.
Step 3: Obtain the Column Reduction β subtract the smallest number in each column of the new table from every number in the column.
Step 4: Test whether an optimum assignment can be made. Determine the minimum number of lines needed to cover (i.e., cross out) all zeros. If the number of lines equals the number of rows, an optimum assignment is possible. In that case, move to the final step.
Step 5: If the number of lines is less than the number of rows, modify the table: β’ Subtract the smallest uncovered number from every uncovered number in the table. β’ Add the smallest uncovered number to the numbers at the intersections of covering lines. β’ Numbers crossed out but not at intersections of cross out lines carry over unchanged to the next table.
Step 6: Repeat steps 4 and 5 unless an optimal table is obtained.
Step 7: Make the assignments. Begin with rows or columns with only one zero. Match items that have zeros, using only one match for each row and each column. Cross out both the row and column for each match.
Hungarian Method Example β Full Step-by-Step Solution
The lecture provides a matrix showing Jobs 1, 2, 3, and 4 with Machines A, B, C, and D:
| JOBS | A | B | C | D |
|---|---|---|---|---|
| 1 | 8 | 6 | 2 | 4 |
| 2 | 6 | 7 | 11 | 10 |
| 3 | 3 | 5 | 7 | 6 |
| 4 | 5 | 10 | 12 | 9 |
Step 1: Select the Row Minimum
| JOBS | A | B | C | D | ROW MIN |
|---|---|---|---|---|---|
| 1 | 8 | 6 | 2 | 4 | 2 |
| 2 | 6 | 7 | 11 | 10 | 6 |
| 3 | 3 | 5 | 7 | 6 | 3 |
| 4 | 5 | 10 | 12 | 9 | 5 |
Step 2: Subtract row minimum and select Column Minimum
| JOBS | A | B | C | D |
|---|---|---|---|---|
| 1 | 6 | 4 | 0 | 2 |
| 2 | 0 | 1 | 5 | 4 |
| 3 | 0 | 2 | 4 | 3 |
| 4 | 0 | 5 | 7 | 4 |
| COL MIN | 0 | 1 | 0 | 2 |
Step 3: Subtract column minimum
| JOBS | A | B | C | D |
|---|---|---|---|---|
| 1 | 6 | 3 | 0 | 0 |
| 2 | 0 | 0 | 5 | 2 |
| 3 | 0 | 1 | 4 | 1 |
| 4 | 0 | 4 | 7 | 2 |
Step 4: Determine minimum lines to cover zeros β Here we have three lines only and rows are 4, so the solution is not optimal.
Step 5: Modify the table β Subtract the smallest value that has not been crossed out (1) from every number that has not been crossed out and add this to numbers at intersections of covering lines.
| JOBS | A | B | C | D |
|---|---|---|---|---|
| 1 | 6+1=7 | 3 | 0 | 0 |
| 2 | 0+1=1 | 0 | 5 | 2 |
| 3 | 0 | 0 | 3 | 0 |
| 4 | 0 | 3 | 6 | 1 |
Step 6: Test again β Determine the minimum number of lines needed to cross out all zeros (4). Since this equals the number of rows, we obtain the optimum assignment.
| JOBS | A | B | C | D |
|---|---|---|---|---|
| 1 | 7 | 3 | 0 | 0 |
| 2 | 1 | 0 | 5 | 2 |
| 3 | 0 | 0 | 3 | 0 |
| 4 | 0 | 3 | 6 | 1 |
Step 7: Make the assignments β Start with rows and columns with only one zero. Match jobs with machines that have 0 costs.
The final assignment according to the Hungarian Method is:
A4, 2B, 1C, and 3D
π Example: Job 1 is assigned to Machine C (cost 2), Job 2 to Machine B (cost 7), Job 3 to Machine D (cost 6), and Job 4 to Machine A (cost 5). Total cost = 2 + 7 + 6 + 5 = 20.
Sequencing
π Definition β Sequencing: Determine the order in which jobs at a work center will be processed.
π Definition β Workstation: An area where one person works, usually with special equipment, on a specialized job.
Summary
Scheduling is the timing and coordination of Operations. Scheduling problems differ in nature because of the system being designed for high volume, intermediate or low volume flow. The next lecture will discuss its complementary and supplementary concept of Sequencing.
β Key Takeaways
Scheduling is the critical tool for timing and coordinating all operations, and its effectiveness directly impacts productivity and cost savings across manufacturing and service systems. Students must understand the distinction between high-volume flow systems, intermediate-volume systems (with their economic run size formula), and low-volume job shops where loading and sequencing become central challenges. The Gantt Chart familyβLoad Chart, Schedule Chart, and Input/Output Control Chartβprovides essential visual tools for managing workloads and tracking progress. The Hungarian Method for the Assignment Model is a must-know technique for optimal one-to-one task-to-resource matching, and students should be able to work through its full step-by-step procedure including row reduction, column reduction, line testing, and table modification. Finally, mastering the seven loading types (infinite, finite, vertical, horizontal, forward, backward, and schedule chart) and the distinction between loading and sequencing is essential for exam success.
π§ Quick Revision Questions
- What is the difference between forward scheduling and backward scheduling, and when would each be used?
- List and briefly explain the seven benefits of effective production scheduling.
- What is the formula for Economic Run Size in intermediate-volume systems, and what do each of its variables represent?
- Describe the step-by-step process of the Hungarian Method for assignment problems, including what you do when the number of covering lines is less than the number of rows.
- What is the difference between infinite loading and finite loading, and how do vertical loading and horizontal loading relate to these two concepts?
π Lecture 42 β SEQUENCING
π Overview: This lecture covers the critical concepts of sequencing jobs at work centers and scheduling operations. It explains priority rules, the Hungarian Method, and Johnsonβs Rule for minimizing completion time. The lecture also addresses maintenance strategies and how effective scheduling forms a core part of operations strategy, ensuring on-time delivery and competitive advantage.
ποΈ Topics Covered
The lecture begins by defining sequencing and workstations, then introduces six priority rules (FCFS, SPT, DD, CR, S/O, Rush) and their assumptions. It provides detailed worked examples comparing FCFS, SPT, DD, and CR rules using data for six jobs. Next, it covers Johnsonβs Rule for two work-center sequencing with a worked example, followed by scheduling difficulties and solutions. Finally, it examines scheduling service operations, cyclical scheduling, and maintenance (breakdown, preventive, predictive), concluding with operations strategy implications.
π Lecture Summary
Sequencing
Sequencing determines the order in which jobs at a work center will be processed. It requires order for sequencing at all work centers as well as sequencing at individual work centers.
A workstation is an area where one person works, usually with special equipment, on a specialized job.
Job time is the time needed for setup and processing of a job.
Priority rules are simple heuristics (commonsense rules) used to select the order in which jobs will be processed. They are classified as:
- Local Rules (pertaining to single workstation)
- Global Rules (pertaining to multiple workstations)
- Job processing times and due dates are important pieces of information
- Job time consists of processing time and setup times
Priority Rules
- FCFS - First Come, First Served: Jobs are processed in the order in which they arrive at a machine or work center.
- SPT - Shortest Processing Time: Jobs are processed according to processing time at a machine or work center, shortest job first.
- DD - Due Date: Jobs are processed according to due date, earliest due date first.
- CR - Critical Ratio: Jobs are processed according to smallest ratio of time remaining until due date to processing time remaining.
- S/O - Slack per Operation: Jobs are processed according to average slack time (time until due date minus remaining time to process). Compute by dividing slack time by number of remaining operations including the current one.
- Rush β Emergency: Emergency or Preferred Customers first.
Assumptions to Priority Rules
- The set of jobs is known, no new jobs arrive after processing begins and no jobs are canceled.
- Setup time is deterministic.
- Processing times are deterministic rather than variables.
- There will be no interruptions in processing such as machine breakdowns, accidents, or worker illnesses.
π Definition β Job Flow Time: The length of time a job is in the shop at a particular workstation or work center.
π Definition β Job Lateness: The length of time the job completion date is expected to exceed the date the job was due or promised to a customer.
π Definition β Makespan: The total time needed to complete a group of jobs. It is the length of time between the start of the first job in the group and the completion of the last job in the group.
π Definition β Average Number of Jobs: Jobs that are considered in a shop are considered to be work in process inventory. π Formula: Average Number of Jobs = Total Flow Time / Makespan
Example
Determine the sequence of jobs, average time flow, average days late, and average number of jobs at the work center for each of these rules: FCFS, SPT, DD, CR.
Example Data:
| JOB | Processing Time | Due Date |
|---|---|---|
| A | 2 | 7 |
| B | 8 | 16 |
| C | 4 | 4 |
| D | 10 | 17 |
| E | 5 | 15 |
| F | 12 | 18 |
Part A: FCFS Assume Jobs arrived in the following order: A-B-C-D-E-F
| Job Sequence | Processing Time (1) | Flow Time (cumulative) (2) | Due Date (3) | Lateness (2)-(3) |
|---|---|---|---|---|
| A | 2 | 2 | 7 | 0 |
| B | 8 | 10 | 16 | 0 |
| C | 4 | 14 | 4 | 10 |
| D | 10 | 24 | 17 | 7 |
| E | 5 | 29 | 15 | 14 |
| F | 12 | 41 | 18 | 23 |
| Total | 41 | 120 | 54 |
- Average Flow time = Total Flow Time / Number of Jobs = 120 / 6 = 20 days
- Average Tardiness = 54 / 6 = 9 days
- Makespan = 41 days
- Average Number of Jobs at workstation = 120 / 41 = 2.93 jobs per workstation
Part B: SPT Rule (Sequence: A-C-E-B-D-F)
| Job Sequence | Processing Time (1) | Flow Time (cumulative) (2) | Due Date (3) | Lateness (2)-(3) |
|---|---|---|---|---|
| A | 2 | 2 | 7 | 0 |
| C | 4 | 6 | 4 | 2 |
| E | 5 | 11 | 15 | 0 |
| B | 8 | 19 | 16 | 3 |
| D | 10 | 29 | 17 | 12 |
| F | 12 | 41 | 18 | 23 |
| Total | 41 | 108 | 40 |
- Average Flow time = 108 / 6 = 18 days
- Average Tardiness = 40 / 6 = 6.67 days
- Makespan = 41 days
- Average Number of Jobs = 108 / 41 = 2.63 jobs per workstation
Summary Part A, B, C, and D:
| Job Sequences Rule | Average Flow Time (Days) | Average Lateness (Days) | Average Number of Jobs |
|---|---|---|---|
| FCFS | 20.00 | 9.00 | 2.93 |
| SPT | 18.00 | 6.67 | 2.63 |
| DD | 18.33 | 6.33 | 2.68 |
| CR | 26.67 | 14.17 | 3.9 |
- Generally Speaking, FCFS and CR rule seem to be the least effective.
- CR is the worst in each aspect of measurement.
- The primary limitation of FCFS is that long jobs will tend to delay other jobs.
- However, in scheduling of service systems, the FCFS has the advantage of simplicity, inherent fairness (first come first served), but also due to non-availability of realistic estimates of processing times for individual jobs.
π‘ Why this matters: SPT consistently gives the lowest average flow time and fewest jobs at the work center, making it the most efficient rule for minimizing work-in-process inventory.
Johnsonβs Rule (Two Work Center Sequencing)
Johnsonβs Rule is a technique for minimizing completion time for a group of jobs to be processed on two machines or at two work centers.
- Minimizes total idle time
- Several conditions must be satisfied
Johnsonβs Rule Conditions:
- Job time must be known and constant
- Job times must be independent of sequence
- Jobs must follow same two-step sequence
- Job priorities cannot be used
- All units must be completed at the first work center before moving to second
Johnsonβs Rule Optimum Sequence:
- List the jobs and their times at each work center
- Select the job with the shortest time
- If the shortest time is at the first work center, schedule that job first
- If the shortest time is at the second work center, schedule that job last
- Break ties arbitrarily
- Eliminate the job from further consideration
- Repeat steps 2 and 3 until all jobs have been scheduled
Johnsonβs Rule Example:
| JOB | Work Center 1 | Work Center 2 |
|---|---|---|
| A | 5 | 5 |
| B | 4 | 3 |
| C | 8 | 9 |
| D | 2 | 7 |
| E | 6 | 8 |
| F | 12 | 15 |
- Select the job with shortest processing time: Job D (2 hours at WC1) β schedule first
- Eliminate row D. Next shortest is Job B (3 hours at WC2) β schedule last
- Eliminate row B. Next: Job A (5 hours at WC1 or WC2, tie) β schedule next available position
- Continue sequencing. Resulting order: D, E, C, F, A, B
- Construct a chart to determine throughput time and idle times at the work centers.
Scheduling Difficulties
- Variability in: a. Setup times b. Processing times c. Interruptions d. Changes in the set of jobs
- No method for identifying optimal schedule
- Scheduling is not an exact science
- Ongoing task for a manager
Minimizing Scheduling Difficulties
- Set realistic due dates
- Focus on bottleneck operations
- Consider lot splitting of large jobs
Scheduling Service Operations
- Appointment systems: Controls customer arrivals for service
- Reservation systems: Estimates demand for service
- Scheduling the workforce: Manages capacity for service
- Scheduling multiple resources: Coordinates use of more than one resource
Cyclical Scheduling
- Hospitals, police/fire departments, restaurants, supermarkets
- Rotating schedules
- Set a scheduling horizon
- Identify the work pattern
- Develop a basic employee schedule
- Assign employees to the schedule
Service Operation Problems
- Cannot store or inventory services
- Customer service requests are random
- Scheduling service involves: customers, workforce, equipment
Maintenance
Maintenance: All activities that maintain facilities and equipment in good working order so that a system can perform as intended.
Breakdown maintenance: Reactive approach; dealing with breakdowns or problems when they occur.
Preventive maintenance: Proactive approach; reducing breakdowns through a program of lubrication, adjustment, cleaning, inspection, and replacement of worn parts.
Reasons for keeping equipment running:
- Avoid production disruptions
- Not add to production costs
- Maintain high quality
- Avoid missed delivery dates
Breakdown Consequences:
- Production capacity is reduced: Orders are delayed
- No production: Overhead continues
- Cost per unit increases: Quality issues
- Product may be damaged
- Safety issues: a. Injury to employees b. Injury to customers
Total Maintenance Cost
Preventive maintenance: Goal is to reduce the incidence of breakdowns or failures in the plant or equipment to avoid the associated costs.
- Preventive maintenance is periodic
- Result of planned inspections
- According to calendar
- After predetermined number of hours
Example 1 β Frequency of breakdown:
| Number of Breakdowns | Frequency of Occurrence |
|---|---|
| 0 | .20 |
| 1 | .30 |
| 2 | .40 |
| 3 | .10 |
If the average cost of a breakdown is Rs.10,000, and the cost of preventative maintenance is Rs.12,500 per month, should we use preventive maintenance?
Example 1 Solution:
| Number of Breakdowns | Frequency of Occurrence | Expected Number of Breakdowns |
|---|---|---|
| 0 | .20 | 0 |
| 1 | .30 | .30 |
| 2 | .40 | .80 |
| 3 | .10 | .30 |
| Total | 1.00 | 1.40 |
Expected cost to repair = 1.4 breakdowns per month Γ Rs.10,000 = Rs.14,000 Preventive maintenance = Rs.12,500 PM results in savings of Rs.1,500 per month
π‘ Why this matters: When the expected breakdown cost exceeds the preventive maintenance cost, preventive maintenance is economically justified.
Predictive Maintenance
Predictive maintenance: An attempt to determine when best to perform preventive maintenance activities.
Total productive maintenance: JIT approach where workers perform preventive maintenance on the machines they operate.
Breakdown Programs
- Standby or backup equipment that can be quickly pressed into service
- Inventories of spare parts that can be installed as needed
- Operators who are able to perform minor repairs
- Repair people who are well trained and readily available to diagnose and correct problems with equipment
Replacement
- Trade-off decisions
- Cost of replacement vs. cost of continued maintenance
- New equipment with new features vs. maintenance
- Installation of new equipment may cause disruptions
- Training costs of employees on new equipment
- Forecasts for demand on equipment may require new equipment capacity
- When is it time for replacement?
Operations Strategy
- Scheduling can hinder or help the Operations Strategy.
- An on-time delivery of a product or service is only possible if the Operations Manager is able to do effective scheduling.
- An ineffective scheduling would result in inefficient use of resources and possible dissatisfied customers.
- Scheduling as an Operations Strategy can provide an organization a competitive advantage over its competitors.
- Time-based competition depends on good scheduling.
- Good design, superior quality, and other elements of a well-run organization are meaningless if effective scheduling is absent from Operations Management Strategy.
- Scheduling is that bank balance which may seem great in numbers but if not used effectively would not make any sense.
β Key Takeaways
Students must remember that the SPT rule consistently yields the lowest average flow time (18 days) and lowest average number of jobs at the work center (2.63) among the priority rules tested. Johnsonβs Rule provides the optimal sequence for two work centers by scheduling the shortest job at WC1 first and the shortest job at WC2 last, minimizing total idle time. Maintenance decisions involve comparing the expected breakdown cost against preventive maintenance cost; in the example, PM saved Rs.1,500 per month. Scheduling is not an exact science but is critical for operations strategyβeffective scheduling ensures on-time delivery and provides a competitive advantage. Finally, service operations require appointment/reservation systems because services cannot be inventoried and demand is random.
π§ Quick Revision Questions
- What are the six priority rules for sequencing, and which one generally gives the lowest average flow time?
- Explain the steps of Johnsonβs Rule for sequencing jobs through two work centers.
- In the FCFS example, what were the average flow time, average tardiness, and makespan for the six jobs?
- When is preventive maintenance economically justified, as shown in the breakdown frequency example?
- Why is scheduling considered a critical part of operations strategy, and what difficulties make it challenging?