π Lecture Summary
Supply Chain
The sequence of organization's facilities, functions, and activities that are involved in producing and delivering a product or service.
Need for Supply Chain Management
- Improve operations
- Increasing levels of outsourcing
- Increasing transportation costs
- Competitive pressures
- Increasing globalization
- Increasing importance of e-commerce
- Complexity of supply chains
- Manage inventories
Benefits of Supply Chain Management
- Lower inventories
- Higher productivity
- Greater agility
- Shorter lead times
- Higher profits
- Greater customer loyalty
Elements of Supply Chain Management
| Element | Typical Issues |
|---|---|
| Customers | Determining what customers want |
| Forecasting | Predicting quantity and timing of demand |
| Design | Incorporating customer wants, manufacturing, and time |
| Processing | Controlling quality, scheduling work |
| Inventory | Meeting demand while managing inventory costs |
| Purchasing | Evaluating suppliers and supporting operations |
| Suppliers | Monitoring supplier quality, delivery, and relations |
| Location | Determining location of facilities |
| Logistics | Deciding how to best move and store materials |
Logistics
The goal of logistic work is to manage the completion of project life cycles, supply chains and resultant efficiencies. Often Logistics is termed as the art and science of managing and controlling the flow of goods, energy, information and other resources like products, services, and people, from the source of production to the marketplace.
It also refers to the movement of materials and information within a facility and to incoming and outgoing shipments of goods and materials in a supply chain.
Logistics is the time related positioning of resources and is commonly seen as a branch of engineering which creates "people systems" rather than "machine systems." It involves the integration of information, transportation, inventory, warehousing, material handling, and packaging.
Important Characteristics of Logistics
- Movement within the facility
- Bar coding
- Incoming and outgoing shipments
- EDI (Electronic Data Interchange)
- Distribution
- JIT Deliveries
Logistics: Evaluating Shipping Alternatives
A situation that arises frequently in some businesses is making a choice between quicker (expensive) shipping alternatives such as overnight or 2-day air and slower but cheaper alternatives. The decision in such cases often focuses on the cost savings of alternatives versus the increased holding cost that results from using the slower alternative.
Often the supplier gets paid on delivery of the product through EDI the very same time the order reaches its destination.
The Incremental Holding Cost incurred by using the slower alternative is computed as follows:
π Formula:
Incremental Holding Cost = H (d/365)
Where:
- H = Annual Holding cost for the item
- d = Time savings in days
- d/365 = fraction of year saved
Logistics Example
Determine the shipping alternative (within Pakistan) for a Karachi based Montessori toy manufacturer: 1 day or 5 days are best when the holding cost of the item is Rs. 100,000 per year and:
- 1 day shipping cost is Rs. 1,500
- 3 day shipping cost is Rs. 600
- 5 day shipping cost is Rs. 500
Solution:
H = Rs. 100,000 per year
Time savings = 2 days using 1 day alternative
Holding cost for additional 2 days = 100,000 Γ (2/365) = Rs. 547.95 β Rs. 548
Or Holding cost per day = Rs. 274
Alternative A (comparing 1 day vs 3 day):
Cost savings = Rs. (1,500 β 600) = Rs. 900
Since the actual cost savings of Rs. 900 is more than the holding cost of Rs. 548, use the 3 day option.
Alternative B (comparing 1 day vs 5 day):
Cost savings = Rs. (1,500 β 500) = Rs. 1,000
Since the actual cost savings of Rs. 1,000 is greater than the holding cost of Rs. 548, use the 5 day option.
Distribution Requirements Planning
Distribution Requirements Planning (DRP) is a system for inventory management and distribution planning. It extends the concepts of MRPII.
π Definition β DRP: A system for inventory management and distribution planning that extends the concepts of MRPII.
Uses of DRP:
Management uses DRP to plan and coordinate:
- Transportation
- Warehousing
- Workers
- Equipment
- Financial flows
Electronic Data Interchange
EDI is the direct transmission of inter-organizational transactions, computer-to-computer, including purchase orders, shipping notices, and debit or credit memos.
π Definition β EDI: The direct transmission of inter-organizational transactions, computer-to-computer, including purchase orders, shipping notices, and debit or credit memos.
Benefits and advantages of EDI:
- Increased productivity
- Reduction of paperwork
- Lead time and inventory reduction
- Facilitation of just-in-time systems
- Electronic transfer of funds
- Improved control of operations
- Reduction in clerical labor
- Increased accuracy
Efficient Consumer Response
Efficient Consumer Response (ECR) is a supply chain management initiative specific to the food industry. ECR reflects companies' efforts to achieve quick response using EDI and bar codes.
π Definition β ECR: A supply chain management initiative specific to the food industry that reflects companies' efforts to achieve quick response using EDI and bar codes.
E-Commerce
E-Commerce is the use of electronic technology to facilitate business transactions.
Successful Supply Chain
- Trust among trading partners
- Effective communications
- Supply chain visibility
- Event-management capability β the ability to detect and respond to unplanned events
- Performance metrics
β Key Takeaways
Supply Chain Management is fundamentally about the flow of information that ensures the effective flow of materials throughout the value chainβfrom suppliers (upstream) to the organization to customers (downstream). The strength of a supply chain equals the strength of its weakest link, and organizations must incorporate customer feedback to avoid losing business. Logistics involves deciding how to best move and store materials, and when evaluating shipping alternatives, managers must compare cost savings against incremental holding costs using the formula H(d/365). DRP extends MRPII concepts for inventory and distribution planning, while EDI enables computer-to-computer transmission of transactions. A successful supply chain requires trust, effective communication, visibility, event management capability, and performance metrics.
π§ Quick Revision Questions
-
What are the eight elements of Supply Chain Management, and what typical issue is associated with each?
-
How do you calculate the incremental holding cost when evaluating shipping alternatives? Use the formula with an example.
-
Explain the difference between DRP and EDI. What are the main uses of each?
-
What is Efficient Consumer Response (ECR) and which industry does it specifically target?
-
List five characteristics of a successful supply chain. Why is trust considered the first requirement?
π Lecture 40 β Supply Chain Management (Contd.)
π Overview: This lecture continues the exploration of Supply Chain Management by focusing on key metrics and frameworks used to analyze and design effective supply chains. It introduces the Supply Chain Operational Reference (SCOR) Metrics, Collaborative Planning Forecasting and Replenishment (CPFR) process, and examines critical challenges like the Bullwhip effect and Velocity, which directly impact supply chain effectiveness.
ποΈ Topics Covered
This lecture covers the Supply Chain Operational Reference (SCOR) Metrics across reliability, flexibility, expenses, and assets/utilization perspectives; the Collaborative Planning Forecasting and Replenishment (CPFR) process with its nine steps; steps for creating an effective supply chain; supply chain performance drivers including velocity; challenges such as trade-offs, Bullwhip effect, Cross-docking, and Delayed differentiation; supply chain issues at strategic, tactical, and operating levels; benefits and drawbacks of supply chain improvements; supplier partnerships; and critical issues in technology management and operations strategy.
π Lecture Summary
Supply Chain Operational Reference (SCOR) Metrics
The Supply Chain Operational Reference (SCOR) Metrics provide a framework for measuring supply chain performance across multiple perspectives. These metrics help operations managers evaluate and improve supply chain effectiveness.
Reliability metrics include on-time delivery, order fulfillment lead time, fill rate (fraction of demand met from stock), and perfect order fulfillment. Flexibility metrics cover supply chain response time and upside production flexibility, reflecting agility to obtain competitiveness. Expenses metrics track supply chain management costs, warranty cost as a percent of revenue, and value added per employee. Assets/utilization metrics measure total inventory days of supply, cash-to-cash cycle time, and net asset turns.
π‘ Why this matters: Supply chain response time often makes or breaks a supply chain.
CPFR
CPFR is an acronym derived from Collaborative Planning, Forecasting and Replenishment. This process focuses on information sharing among trading partners, allows forecasts to be frozen and then converted into a shipping plan, and eliminates typical order processing.
The CPFR Process consists of nine steps:
- Step 1 β Front-end agreement
- Step 2 β Joint business plan
- Steps 3-5 β Sales forecast
- Steps 6-8 β Order forecast collaboration
- Step 9 β Order generation/delivery execution
Creating an Effective Supply Chain
To create an effective supply chain, organizations must:
- Develop strategic objectives and tactics
- Integrate and coordinate activities in the internal supply chain
- Coordinate activities with suppliers and customers
- Coordinate planning and execution across the supply chain
- Form strategic partnerships
Supply Chain Performance Drivers
The key supply chain performance drivers are: Quality, Cost, Flexibility, Velocity, and Customer service.
Velocity
Velocity has two important dimensions in supply chain management:
- Inventory velocity: The rate at which inventory (material) goes through the supply chain.
- Information velocity: The rate at which information is communicated in a supply chain.
Challenges to an Effective Supply Chain Management
The main challenges include:
- Barriers to integration of organizations
- Getting top management on board
- Dealing with trade-offs
- Small businesses
- Variability and uncertainty
- Long lead times
Trade-offs
Several important trade-offs exist in supply chain management:
- Cost-customer service: Involves Disintermediation β reducing one or more steps in a supply chain by cutting out one or more intermediaries.
- Lot-size-inventory: Involves the Bullwhip effect β representing that inventories are progressively larger moving backward through the supply chain.
- Inventory-transportation costs: Involves Cross-docking β goods arriving at a warehouse from a supplier are unloaded from the supplier's truck and loaded onto outbound trucks, avoiding warehouse storage.
- Lead time-transportation costs
- Product variety-inventory: Involves Delayed differentiation β production of standard components and subassemblies, which are held until late in the process to add differentiating features.
π Definition β Bullwhip effect: The phenomenon where inventories are progressively larger moving backward through the supply chain. π Definition β Cross-docking: A practice where goods arriving at a warehouse from a supplier are unloaded from the supplier's truck and loaded directly onto outbound trucks, avoiding warehouse storage. π Definition β Delayed differentiation: Production of standard components and subassemblies, which are held until late in the process to add differentiating features. π Definition β Disintermediation: Reducing one or more steps in a supply chain by cutting out one or more intermediaries.
Supply Chain Issues
Supply chain issues are categorized at three levels:
- Strategic Issues: Design of the supply chain, partnering
- Tactical Issues: Quality control, production planning and control, inventory policies, purchasing policies
- Operating Issues: Production policies, transportation policies, quality policies
Supply Chain Benefits and Drawbacks
This table outlines problems, potential improvements, benefits, and possible drawbacks:
| Problem | Potential Improvement | Benefits | Possible Drawbacks |
|---|---|---|---|
| Large inventories | Smaller, more frequent deliveries | Reduced holding costs | Traffic congestion, increased costs |
| Long lead times | Delayed differentiation, Disintermediation | Quick response | May not be feasible, may need to absorb functions |
| Large number of parts | Modular | Fewer parts, simpler ordering | Less variety |
| Cost, Quality | Outsourcing | Reduced cost, higher quality | Loss of control |
| Variability | Shorter lead times, better forecasts | Able to match supply and demand | Less variety |
Supplier Partnerships
Ideas from suppliers could lead to improved competitiveness by:
- Reducing cost of making the purchase
- Increasing Revenues
- Enhancing Performance
Critical Issues
Key critical issues in supply chain management include:
- Technology management: Considering Benefits and Risks
- Strategic importance: Focusing on Quality, Cost, Agility, Customer service, and Competitive advantage
Operations Strategy
Two key points about operations strategy in supply chain management:
- SCM creates value through changes in time, location and quantity.
- SCM creates competitive advantage by integrating and streamlining the diverse range of activities that involve purchasing, internal inventory, transfers and physical distribution.
β Key Takeaways
Students must remember that SCOR Metrics provide a comprehensive framework across reliability, flexibility, expenses, and assets/utilization for measuring supply chain performance, while CPFR facilitates collaboration through its nine-step process. The Bullwhip effect causes inventories to grow progressively larger moving backward through the supply chain, and Velocity has both inventory and information dimensions that are critical for efficiency. Key trade-offs include cost-customer service (disintermediation), lot-size-inventory (Bullwhip effect), inventory-transportation (cross-docking), and product variety-inventory (delayed differentiation). Supply chain issues span strategic, tactical, and operating levels, and organizations often fail in SCM implementation due to lack of employee training and top management commitment.
π§ Quick Revision Questions
- What are the four perspectives of the SCOR Metrics and what does each measure?
- List the nine steps of the CPFR process in order.
- What is the Bullwhip effect and how does it impact inventory levels in the supply chain?
- Define and distinguish between inventory velocity and information velocity.
- Explain how delayed differentiation and cross-docking address different trade-offs in supply chain management.
π Lecture 41 β Scheduling
π Overview: This lecture introduces the concept of scheduling as a critical tool for productivity in both manufacturing and service industries. It explains how scheduling applies to high-volume, intermediate-volume, and low-volume (job shop) systems, and covers key techniques including Gantt Charts, the Assignment Method (Hungarian Method), and priority rules for sequencing.
ποΈ Topics Covered
The lecture defines scheduling and its benefits, then distinguishes between high-volume flow systems, intermediate-volume systems (with economic run size formulas), and low-volume job-shop systems. It covers loading and sequencing, explains Gantt Load Charts and Schedule Charts, details the Assignment Method using the Hungarian Method with a worked numerical example, and introduces common loading types (infinite, finite, vertical, horizontal, forward, backward).
π Lecture Summary
Scheduling
Scheduling is an important tool for manufacturing and service industries where it can have a major impact on the productivity of a process. In manufacturing, the purpose of scheduling is to minimize the production time and costs, by telling a production facility what to make, when, with which staff, and on which equipment. In service industries, such as airlines and public transport, scheduling aims to maximize the efficiency of the operation and reduce costs. Modern computerized scheduling tools outperform older manual methods by providing graphical interfaces to visually optimize real-time workloads. Companies use backward scheduling (planning from the due date to determine the start date) and forward scheduling (planning from the start date to determine the due date).
π Definition β Scheduling: Establishing the timing of the use of equipment, facilities and human activities in an organization.
Benefits of Scheduling
- Cost savings
- Increases in productivity The benefits of production scheduling include: Process change-over reduction, Inventory reduction/leveling, Reduced scheduling effort, Increased production efficiency, Labor load leveling, Accurate delivery date quotes, and Real time information.
High-Volume Systems
A flow system is a high-volume system with standardized equipment and activities. Flow-shop scheduling is the scheduling for such high-volume flow systems.
Scheduling Manufacturing Operations
The lecture categorizes operations into four types: High-volume, Intermediate-volume, Low-volume, and Service operations.
High-Volume Success Factors
- Process and product design
- Preventive maintenance
- Rapid repair when breakdown occurs
- Optimal product mixes
- Minimization of quality problems
- Reliability and timing of supplies
Intermediate-Volume Systems
Outputs are between standardized high-volume systems and made-to-order job shops. Key considerations include run size, timing, and sequence of jobs.
π Formula: Economic run size β ( Q = \sqrt{\frac{2DS}{H(1 - \frac{d}{p})}} ) β where D = demand, S = setup cost, H = holding cost, d = demand rate, p = production rate. This determines the optimal quantity to produce in one run.
Scheduling Low-Volume Systems
- Loading: assignment of jobs to process centers
- Sequencing: determining the order in which jobs will be processed
- Job-shop scheduling: Scheduling for low-volume systems with many variations in requirements
Gantt Load Chart
A Gantt chart is used as a visual aid for loading and scheduling. A Load chart is a type of Gantt chart that shows the loading and idle times for a group of machines or list of departments. A Schedule chart is a type of Gantt chart that shows the orders or jobs in progress and whether they are on schedule. An Input/Output Control Chart is a type of control chart that shows management of work flow and queues at the work centers.
Loading Types
- Infinite loading: Jobs are assigned to work centers without regard to the capacity of the work center.
- Finite loading: Jobs are assigned to work centers with regard to the capacity of the work center and job processing times.
- Vertical loading: Loading jobs at a work center, job by job, usually according to some priority criterion, using infinite loading.
- Horizontal loading: Loading each job on all work centers it will require, then the next job on all work centers, according to some priority, using finite loading.
- Forward scheduling: Scheduling ahead, from some point in time.
- Backward scheduling: Scheduling by working backwards from the due date.
- Schedule chart: A Gantt chart that shows the orders or jobs in progress and whether they are on schedule.
Assignment Method of Linear Programming
The Assignment Model is a type of linear programming model for optimal assignment of tasks and resources. The Hungarian method is the method of assigning jobs by a one-for-one matching to identify the lowest cost solution.
Hungarian Method Steps:
- Arrange cost information in tabular form.
- Row Reduction: Subtract the smallest number in each row from every number in that row. Enter results in a new table.
- Column Reduction: Subtract the smallest number in each column of the new table from every number in that column.
- Test for optimum: Determine the minimum number of lines needed to cover (cross out) all zeros. If the number of lines equals the number of rows, an optimum assignment is possible. Proceed to step 7.
- Modify the table (if lines < rows):
- Subtract the smallest uncovered number from every uncovered number.
- Add the smallest uncovered number to numbers at the intersections of covering lines.
- Numbers crossed out but not at intersections carry over unchanged.
- Repeat steps 4 and 5 until optimal.
- Make assignments: Begin with rows or columns with only one zero. Match items that have zeros, using only one match per row and per column. Cross out both the row and column for each match.
Hungarian Method Example: Given the cost matrix for Jobs 1-4 and Machines A-D:
| Jobs | A | B | C | D |
|---|---|---|---|---|
| 1 | 8 | 6 | 2 | 4 |
| 2 | 6 | 7 | 11 | 10 |
| 3 | 3 | 5 | 7 | 6 |
| 4 | 5 | 10 | 12 | 9 |
Step 1: Row Reduction (subtract row minimum: row1=2, row2=6, row3=3, row4=5)
| Jobs | A | B | C | D |
|---|---|---|---|---|
| 1 | 6 | 4 | 0 | 2 |
| 2 | 0 | 1 | 5 | 4 |
| 3 | 0 | 2 | 4 | 3 |
| 4 | 0 | 5 | 7 | 4 |
Step 2: Column Reduction (subtract column minimum: colA=0, colB=1, colC=0, colD=2)
| Jobs | A | B | C | D |
|---|---|---|---|---|
| 1 | 6 | 3 | 0 | 0 |
| 2 | 0 | 0 | 5 | 2 |
| 3 | 0 | 1 | 4 | 1 |
| 4 | 0 | 4 | 7 | 2 |
Step 3: Test β Minimum lines to cover zeros = 3 (rows 1-4 β not optimal). Smallest uncovered number = 1. Step 4: Modify table β Subtract 1 from uncovered numbers, add 1 to intersections. Result:
| Jobs | A | B | C | D |
|---|---|---|---|---|
| 1 | 7 | 3 | 0 | 0 |
| 2 | 1 | 0 | 5 | 2 |
| 3 | 0 | 0 | 3 | 0 |
| 4 | 0 | 3 | 6 | 1 |
Step 5: Test β Minimum lines to cover zeros = 4 (equals rows β optimal). Step 6: Make assignments β Start with rows/columns with one zero: Row1 has two zeros (C and D), Row2 has one zero (B), Row3 has two zeros (A and D), Row4 has one zero (A). Assign Row2βB, Row4βA, then Row1βC, Row3βD. Final assignment: 4A, 2B, 1C, 3D
Sequencing
Sequencing determines the order in which jobs at a work center will be processed. A Workstation is an area where one person works, usually with special equipment, on a specialized job.
β Key Takeaways
Scheduling is the timing and coordination of operations, with different approaches for high-volume flow systems, intermediate-volume batch systems, and low-volume job shops. The Gantt Load Chart is a key visual tool for loading and tracking work center status. The Hungarian Method provides a systematic, step-by-step linear programming approach (row reduction, column reduction, line testing, and table modification) to achieve optimal one-to-one assignment of jobs to machines at the lowest total cost. Key loading types include infinite, finite, vertical, and horizontal loading, as well as forward and backward scheduling. Sequencing determines the order of job processing at workstations, and scheduling problems differ fundamentally based on the production system's volume and customization level.
π§ Quick Revision Questions
- What is the difference between forward scheduling and backward scheduling?
- List the seven types of loading discussed in the lecture.
- What is the purpose of the Hungarian Method, and what are the first two steps in applying it?
- In the Hungarian Method, how do you test whether an optimum assignment has been reached?
- What is the difference between a Load Chart and a Schedule Chart in the context of Gantt Charts?
π Lecture 42 β SEQUENCING
π Overview: This lecture provides a comprehensive understanding of scheduling and sequencing operations using the Hungarian Method and Johnson's Rules. Students learn to apply priority rules for effective scheduling at work centers, understand the trade-offs between different sequencing methods, and develop an operations strategy integrating both scheduling and sequencing. The lecture also covers maintenance strategies essential for ensuring scheduled operations run without disruption.
ποΈ Topics Covered
The lecture defines sequencing and priority rules (FCFS, SPT, DD, CR, S/O, Rush), explains assumptions for priority rules, and provides detailed examples applying FCFS and SPT rules with calculations of average flow time, average tardiness, and average number of jobs. It introduces Johnson's Rule for two-work-center sequencing with a worked example, discusses scheduling difficulties and minimization strategies, covers scheduling service operations and cyclical scheduling, and concludes with maintenance (breakdown vs. preventive), predictive maintenance, replacement decisions, and operations strategy implications.
π Lecture Summary
Sequencing
Sequencing determines the order in which jobs at a work center will be processed. It requires order for sequencing at all work centers as well as sequencing at individual work centers.
π Definition β Sequencing: Determine the order in which jobs at a work center will be processed.
π Definition β Workstation: An area where one person works, usually with special equipment, on a specialized job.
π Definition β Job time: Time needed for setup and processing of a job.
π Definition β Priority rules: Simple heuristics (commonsense rules) used to select the order in which jobs will be processed.
Priority Rules
Priority rules are categorized as local rules (pertaining to single workstation) and global rules (pertaining to multiple workstation). Job processing times and due dates are important pieces of information. Job time consists of processing time and setup times.
The six priority rules are:
- FCFS - First Come, First Served: Jobs are processed in the order in which they arrive at a machine or work center.
- SPT - Shortest Processing Time: Jobs are processed according to processing time at a machine or work center, shortest job first.
- DD - Due Date: Jobs are processed according to due date, earliest due date first.
- CR - Critical Ratio: Jobs are processed according to smallest ratio of time remaining until due date to processing time remaining.
- S/O - Slack per Operation: Jobs are processed according to average slack time (time until due date minus remaining time to process). Compute by dividing slack time by number of remaining operations including the current one.
- Rush β Emergency: Emergency or Preferred Customers first.
Assumptions to Priority Rules
The assumptions for applying priority rules are: the set of jobs is known, no new jobs arrive after processing begins and no jobs are canceled; setup time is deterministic; processing times are deterministic rather than variables; there will be no interruptions in processing such as machine breakdowns, accidents, or worker illnesses.
Definitions
π Definition β Job Flow Time: The length of time a job is in the shop at a particular workstation or work center.
π Definition β Job Lateness: The length of time the job completion date is expected to exceed the date the job was due or promised to a customer.
π Definition β Makespan: The total time needed to complete a group of jobs. It is the length of time between the start of the first job in the group and the completion of the last job in the group.
π Formula: Average Number of Jobs = Total Flow Time / Makespan
Example β Sequencing with Priority Rules
Determine the sequence of jobs, average time flow, average days late, and average number of jobs at the work center for each rule: FCFS, SPT, DD, and CR.
Example Data: Jobs A (Processing Time 2, Due Date 7), B (8, 16), C (4, 4), D (10, 17), E (5, 15), F (12, 18).
Part A: FCFS Rule Assume jobs arrived in order: A-B-C-D-E-F
| JOB Sequence | Processing Time (1) | Flow Time (cumulative) (2) | Due Date (3) | Lateness (2)-(3) |
|---|---|---|---|---|
| A | 2 | 2 | 7 | 0 |
| B | 8 | 10 | 16 | 0 |
| C | 4 | 14 | 4 | 10 |
| D | 10 | 24 | 17 | 7 |
| E | 5 | 29 | 15 | 14 |
| F | 12 | 41 | 18 | 23 |
| Total | 41 | 120 | 54 |
π Example Calculation (FCFS):
- Average Flow time = Total Flow Time / Number of Jobs = 120 / 6 = 20 days
- Average Tardiness = 54 / 6 = 9 days
- Makespan = 41 days
- Average Number of Jobs at workstation = 120 / 41 = 2.93 jobs per workstation
Part B: SPT Rule Sequence is A-C-E-B-D-F
| JOB Sequence | Processing Time (1) | Flow Time (cumulative) (2) | Due Date (3) | Lateness (2)-(3) |
|---|---|---|---|---|
| A | 2 | 2 | 7 | 0 |
| C | 4 | 6 | 4 | 2 |
| E | 5 | 11 | 15 | 0 |
| B | 8 | 19 | 16 | 3 |
| D | 10 | 29 | 17 | 12 |
| F | 12 | 41 | 18 | 23 |
| Total | 41 | 108 | 40 |
π Example Calculation (SPT):
- Average Flow time = 108 / 6 = 18 days
- Average Tardiness = 40 / 6 = 6.67 days
- Makespan = 41 days
- Average Number of Jobs at workstation = 108 / 41 = 2.63 jobs per workstation
Summary of All Rules:
| Rule | Average Flow Time (Days) | Average Lateness (Days) | Average Number of Jobs |
|---|---|---|---|
| FCFS | 20.00 | 9.00 | 2.93 |
| SPT | 18.00 | 6.67 | 2.63 |
| DD | 18.33 | 6.33 | 2.68 |
| CR | 26.67 | 14.17 | 3.90 |
Key Observations:
- Generally, FCFS and CR rules seem to be the least effective.
- CR is the worst in each aspect of measurement.
- The primary limitation of FCFS is that long jobs will tend to delay other jobs.
- However, in scheduling of service systems, FCFS has the advantage of simplicity, inherent fairness (first come first served), and non-availability of realistic estimates of processing times for individual jobs.
π‘ Why this matters: Choosing the right priority rule directly impacts customer satisfaction (tardiness), resource utilization (average jobs at workstation), and total production time (makespan). SPT generally performs best for minimizing flow time and work-in-process.
Johnson's Rule (Two Work Center Sequencing)
π Definition β Johnson's Rule: A technique for minimizing completion time for a group of jobs to be processed on two machines or at two work centers.
Johnson's Rule minimizes total idle time, but several conditions must be satisfied.
Johnson's Rule Conditions:
- Job time must be known and constant
- Job times must be independent of sequence
- Jobs must follow same two-step sequence
- Job priorities cannot be used
- All units must be completed at the first work center before moving to second
Johnson's Rule Optimum Sequence:
- List the jobs and their times at each work center
- Select the job with the shortest time
- Eliminate the job from further consideration
- Repeat steps 2 and 3 until all jobs have been scheduled
Johnson's Rule Example:
| JOB | Work Center 1 (Hours) | Work Center 2 (Hours) |
|---|---|---|
| A | 5 | 5 |
| B | 4 | 3 |
| C | 8 | 9 |
| D | 2 | 7 |
| E | 6 | 8 |
| F | 12 | 15 |
π Example (Johnson's Rule):
- Select job with shortest processing time: Job D (2 hours at WC1). Since shortest time is at WC1, schedule D first.
- Eliminate Job D. Next shortest is Job B (3 hours at WC2). Since shortest time is at WC2, schedule B last.
- Next shortest: Job A (5 hours at WC1 and WC2 β tie). Schedule A next at beginning after D or at end before B. Place A at beginning.
- Continue: Job E (6 hours at WC1) β place next at beginning. Job C (8 hours at WC1) β place next. Job F (12 hours at WC1) β place last remaining before B.
- Final sequence: D β E β C β F β A β B
- Construct a chart to determine the throughput time and idle times at the work centers.
Scheduling Difficulties
Scheduling difficulties include variability in setup times, processing times, interruptions, and changes in the set of jobs. There is no method for identifying optimal schedule. Scheduling is not an exact science and remains an ongoing task for a manager.
Minimizing Scheduling Difficulties
To minimize scheduling difficulties: set realistic due dates, focus on bottleneck operations, and consider lot splitting of large jobs.
Scheduling Service Operations
Scheduling service operations includes: appointment systems (controls customer arrivals for service), reservation systems (estimates demand for service), scheduling the workforce (manages capacity for service), and scheduling multiple resources (coordinates use of more than one resource).
Cyclical Scheduling
Cyclical scheduling is used in hospitals, police/fire departments, restaurants, and supermarkets. Steps include: rotating schedules, setting a scheduling horizon, identifying the work pattern, developing a basic employee schedule, and assigning employees to the schedule.
Service Operation Problems
Service operation problems include: cannot store or inventory services, customer service requests are random, and scheduling service involves customers, workforce, and equipment.
Maintenance
π Definition β Maintenance: All activities that maintain facilities and equipment in good working order so that a system can perform as intended.
π Definition β Breakdown maintenance: Reactive approach; dealing with breakdowns or problems when they occur.
π Definition β Preventive maintenance: Proactive approach; reducing breakdowns through a program of lubrication, adjustment, cleaning, inspection, and replacement of worn parts.
Maintenance Reasons for keeping equipment running: avoid production disruptions, not add to production costs, maintain high quality, and avoid missed delivery dates.
Breakdown Consequences include: production capacity is reduced (orders are delayed); no production while overhead continues; cost per unit increases (quality issues); product may be damaged; and safety issues (injury to employees or customers).
Preventive Maintenance goal is to reduce the incidence of breakdowns or failures. Preventive maintenance is periodic, the result of planned inspections, according to calendar, or after a predetermined number of hours.
Example 1: If the average cost of a breakdown is Rs.10,000, and the cost of preventative maintenance is Rs.12,500 per month, should we use preventive maintenance?
| Number of Breakdowns | Frequency of Occurrence | Expected Number of Breakdowns |
|---|---|---|
| 0 | 0.20 | 0 |
| 1 | 0.30 | 0.30 |
| 2 | 0.40 | 0.80 |
| 3 | 0.10 | 0.30 |
| Total | 1.00 | 1.40 |
π Example Calculation:
- Expected cost to repair = 1.4 breakdowns per month Γ Rs.10,000 = Rs.14,000
- Preventive maintenance cost = Rs.12,500
- PM results in savings of Rs.1,500 per month β Yes, use preventive maintenance.
Predictive Maintenance is an attempt to determine when best to perform preventive maintenance activities.
Total productive maintenance is a JIT approach where workers perform preventive maintenance on the machines they operate.
Breakdown Programs include: standby or backup equipment, inventories of spare parts, operators who can perform minor repairs, and well-trained repair people.
Replacement
Replacement involves trade-off decisions between cost of replacement vs. cost of continued maintenance, new equipment features vs. maintenance, disruption from installation, training costs, demand forecasts, and determining when it is time for replacement.
Operations Strategy
Scheduling can hinder or help the Operations Strategy. On-time delivery is only possible with effective scheduling. Ineffective scheduling results in inefficient resource use and dissatisfied customers. Scheduling as an operations strategy can provide a competitive advantage. Time-based competition depends on good scheduling. Good design, superior quality, and other elements are meaningless if effective scheduling is absent from the operations management strategy.
β Key Takeaways
Sequencing prioritizes job order at work centers using heuristics like FCFS, SPT, DD, and CR, with SPT generally producing the lowest average flow time and work-in-process but potentially delaying longer jobs. Johnson's Rule provides an optimal sequence for two work centers by minimizing makespan and idle time. Preventive maintenance should be adopted when its monthly cost is less than the expected breakdown repair cost per month. Scheduling difficulties arise from variability and lack of optimal methods, requiring realistic due dates and bottleneck focus. Effective scheduling is a strategic competitive advantage that enables time-based competition and customer satisfaction.
π§ Quick Revision Questions
- What is the difference between FCFS and SPT priority rules, and which typically results in lower average flow time?
- Calculate the average number of jobs at a workstation given a total flow time of 150 days and a makespan of 50 days.
- Under what specific condition should a preventive maintenance program be adopted instead of a breakdown maintenance approach?
- List the five conditions that must be satisfied for Johnson's Rule to be applicable in two-work-center sequencing.
- Describe three strategies a manager can use to minimize scheduling difficulties in job shop environments.
π Lecture 43 β Project Management
π Overview: This lecture introduces the fundamental concepts of Project Management, distinguishing it from ongoing operations. It covers key success factors, administrative issues, network diagrams, the project life cycle, and the roles and responsibilities of a project manager. Understanding these principles is crucial for effectively planning, executing, and controlling unique, time-bound endeavors.
ποΈ Topics Covered
The lecture begins by defining projects and project management, highlighting their distinguishing characteristics and key success factors. It then explores major administrative issues and introduces project management tools like Gantt charts and network diagrams (Activity on Arrow and Activity on Node). The discussion continues with the project life cycle, the responsibilities and qualifications of a project manager, and the Work Breakdown Structure (WBS). Finally, it covers PERT and CPM techniques, project scope, and the concept of scope creep.
π Lecture Summary
Projects
Projects are unique, one-time (temporary) operations designed to accomplish a specific set of objectives in a limited time frame. This contrasts with operations, which are permanent or semi-permanent ongoing functional work to create the same product or service repeatedly. The management of these two systems is very different, hence the development of project management.
Project Management
Project Management is the organizing and managing resources in such a way that these resources deliver all the work required to complete a project within defined scope, time, and cost constraints.
Distinguishing characteristics of Project Management:
- How is it different?
- Limited time frame
- Narrow focus, specific objectives
- Less bureaucratic
- Why is it used?
- Special needs
- Pressures for new or improved products or services
- Important Key Metrics:
- Time
- Cost
- Performance objectives
Key Success Factors
The key success factors for a project are:
- Top-down commitment
- Having a capable project manager
- Having time to plan
- Careful tracking and control
- Good communications
Project Management has certain major administrative issues, such as executive responsibilities, project selection, project manager selection, organizational structure, organizational alternatives, managing within a functional unit, assigning a coordinator, and using a matrix organization with a project leader.
Project Management: Hospital
The lecture provides an example of setting up a hospital facility. The project managers are required to list possible activities, which are then represented in a Gantt Chart (Planning and Scheduling) and a Network Diagram (AON and AOA activities). The activities include: locate new facilities, interview staff, hire and train staff, select and order machinery, remodel and install phones, and start patient examination/startup.
Network Diagrams and Conventions
- Activity on Arrow (AOA): The network diagram convention in which arrows designate activities.
- Activity on Node (AON): The network diagram convention in which the nodes designate the activities.
- Activities: Project steps that consume or utilize resources (and or time).
- Events: The starting and finishing of activities designated by nodes in the Activity on Arrow notation.
- Path: Sequence of activities that leads from the starting node to the finishing node.
- Critical path: The longest path; determines expected project duration.
- Critical activities: Activities on the critical path.
- Slack: Allowable slippage for a path; the difference between the length of the path and the length of the critical path.
π Formula: Slack = (Length of non-critical path) - (Length of critical path) β This calculates the amount of time a path can be delayed without affecting the overall project duration.
π Example: Given a project with three paths with lengths of 18, 20, and 14 weeks:
- The critical path is the longest path at 20 weeks.
- Path 1-2-3-4-5-6 (18 weeks) has a slack of 18 - 20 = 2 weeks.
- Path 1-3-5-6 (14 weeks) has a slack of 14 - 20 = 6 weeks.
Project Life Cycle
The Project Life Cycle comprises a new concept idea for a unique activity, which is then evaluated through feasibility reports, planned with a certain sequence of activities, executed, and terminated after the project has been completed or shelved. All stages of the project life cycle are administered and handled by a competent project management team or project managers.
Planning and Scheduling involves the following key decisions:
- Deciding which projects to implement
- Selecting a project manager
- Selecting a project team
- Planning and designing the project
- Managing and controlling project resources
- Deciding if and when a project should be terminated
Responsibilities of a Project Manager
A Project Manager is responsible for project management, including technical and financial analysis. They are expected to have qualifications such as PMP certification, and CFM, CFA, and CFP certifications. They should be skilled in financial evaluation, investment analysis, and cost-benefit analysis. Project managers must focus on ethical issues and avoid:
- Temptation to understate costs
- Withholding information
- Misleading status reports
- Falsifying records
- Compromising workersβ safety
- Approving substandard work
Work Breakdown Structure
A project is different from operations due to its unique nature. A good project management practice is to break down the project into sublevels or groups of similar activities. These sublevels or groups of similar activities are called the Work Breakdown Structure (WBS). The WBS usually represents a parent-child activity relationship with the relationship between a parent and child level being easily identifiable. It allows a project manager to incorporate more administrative control over the project activities.
PERT and CPM
PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are project management techniques that:
- Graphically display project activities
- Estimate how long the project will take
- Indicate most critical activities
- Show where delays will not affect the project
Advantages of PERT:
- Forces managers to organize
- Provides graphic display of activities
- Identifies critical activities
- Identifies slack activities
Limitations of PERT:
- Important activities may be omitted
- Precedence relationships may not be correct
- Estimates may include a fudge factor
- May focus solely on critical path
Project Scope and Scope Creep
Project Scope refers to the total work needed out of a project. The primary tool required to describe project scope is the Work Breakdown Structure. Often projects suffer from an irritant known as scope creep, which is the unnecessary extension of project scope that prevents the project from being completed within budget and time limits. Organizations incorporate special management techniques to isolate and eliminate scope creep.
- Technical Scope Creep (Gold Plating): The unfortunate tendency of the technical side to add certain avoidable and costly features to make a product or service more powerful and attractive.
- Business Scope Creep (Customer Pleasing): The tendency of business managers to overdo the customer relationship. π‘ Why this matters: A pragmatic strategy to avoid scope creep is to be judicious about the original project scope and religiously avoid uncalled-for business or technical additions.
β Key Takeaways
The key takeaway is that a project is a unique, temporary endeavor, fundamentally different from ongoing operations, requiring specialized management. The success of a project hinges on identifying the critical pathβthe longest sequence of activities that dictates the project's durationβand calculating slack for other paths. The Work Breakdown Structure (WBS) is an essential tool for breaking down a project into manageable components, while PERT and CPM are powerful techniques for scheduling, analyzing, and controlling projects. Finally, a project manager must be vigilant against "scope creep" and uphold high ethical standards to ensure the project is completed on time, within budget, and to the required performance specifications.
π§ Quick Revision Questions
- What are the three key metrics (constraints) of Project Management?
- How is a "critical path" defined in a network diagram, and what is "slack"?
- Describe the difference between an Activity on Arrow (AOA) and an Activity on Node (AON) network diagram.
- What is the purpose of a Work Breakdown Structure (WBS)?
- Distinguish between "technical scope creep" (gold plating) and "business scope creep" (customer pleasing).